General Information

TitleInformation
LicenseeSeminole Electric Cooperative, Inc (SECI) and JEA
Certification #                                    TA 90-08
Date Certified06/12/1991
DescriptionThis transmission line begins at SECI's Seminole Generating Station and connects to Clay Electric Cooperative's Riverview, Florahome, Keystone and Black Creek Substations, ending at the JEA's Firestone Substation.
Line Length70 Miles
Voltage230 kV
Counties Crossed:Putnam and Duval
DistrictsFlorida Department of Environmental Protection Northeast District
St. Johns River Water Management District

 

Facility State Documents

Facility Document(s)Description
Conditions of CertificationFacility License
Post-Certification Submittal SummarySummary of Submittals Required by Conditions
ModificationsFinal Orders Modifying the Conditions
Amendments Amendment Approval Letters
Final OrderOriginal Final Order of Certification
Site Certification Application *Original and Supplemental Facility Application(s)

* Please note that this link goes to the OCULUS logon page - click on PUBLIC OCULUS LOGIN to view the application sections

Last Modified: Thursday, Oct 12, 2023 - 01:36pm